The all important and space defining phases of insulation and drywall have begun. We are "pushing" our schedule, hoping to close on or around 1 August.
Several issues have occurred almost simultaneously... one involving the order of the garage door, the other related to the order of the interior doors and another concerning the window sills in the "old house."
The garage door orders were somehow 'lost' at the manufacturer, Clopay, and will now take an additional three weeks before delivery. They have agreed to discount the cost by $100.00, to offset one month's POD rental.
The interior door order was not submitted, probably an oversight on my part, but has now been "pushed through," at BFS. We expect the doors to be delivered sometime around July 10th.
Photos
|
Batten style insulation will be used throughout both old and new areas. They used two layers of 11 -R in the walls of the 2 "old" rooms. |
|
|
They knocked out the insulating in about 6 hours, and made it look easy. |
|
|
The duct work of Tri County air over the ceiling of the family room. |
|
|
The application of R-22 (R-11 x 2) should be plenty, as these walls will be 12 inches thick after the sheetrock is applied. |
|