More like 3 years + 1 week lol, but since I am only referring to the building of the house we will call it week 1. Attached are the house elevations and floor plan. These aren’t the final copies, we actually had a few changes, but they are the only ones I have on this computer. We didn’t like the cut of the roof in the back, so that changed and we added on a walkway across the back connecting all the patios.
The inspector came out and approved the footers and we had them poured on Friday. Next step is the stem walls and they are hoping to have them approved/poured by the end of this week. We also have plumbing starting this week. We have 2 electricians we are talking to, we need to officially pick one. Then, they will need to stub in for the island (I think that is the only thing they need to do before foundation is finished).
We are still waiting to hear back from the bank about the appraisal. If all goes well with that, then we should be good to go with the loan.